Project #113 - Kolb Road Connection to Sabino

Picture
Location
Tanque Verde and Sabino Canyon Rd south to Kolb  
Status
In Design  
Total Estimated Project Cost
$21,224,700.00  
Expenditures to Date Through 4/30/2015
$7,838,196.00  
Estimated date of completion as of 2/11/2015
12/31/2016  
Project Contact
Joe Chase (837-6619)  

Description
This project was divided into two Phases: Phase 1. Work on the intersection of Sabino Canyon Road and Tanque Verde and Phase 2. Connecting Sabino to Kolb Road.

Phase 1: Widening and reconstruction of the existing intersection to accommodate additional through lanes for north and south bound travel along with pedestrian, bicycle, landscape, and drainage improvements (completed 9/2012).
Phase 2: The scope consists of designing and constructing a roadway that connects Sabino Canyon Road from Tanque Verde to Kolb Road. The new roadway will consist of 4 travel lanes, 2 bridges, raised medians, noise walls, a storm drain system, landscaping, bicycle lanes, sidewalk, and multi-use paths.
This project creates an additional north/south arterial corridor that will alleviate the congestion at the Grant/Kolb/Tanque Verde intersection by roughly 14%. That in turn will improve the air quality and level of service for the intersection while also reducing emergency response time to residents in the Udall Neighborhood Association.
For additional information see: Kolb Road: Connection to Sabino Canyon Road  
Additional Info
 
Designation(s)
City of Tucson, Street Work, Streetscape Work, Capital Improvement Project  
Last Update
5/15/2015  

Project #113 - Status

12-May-15 FHWA EA Comments being addressed along with 100% plan comments.
14-Apr-15 Draft EA Revised Again Before FHWA Can Begin 1st Review.
11-Mar-15 The project status is the same as the previous month.
13-Feb-15 Draft EA under final ADOT review.

13-Jan-15 Preparing for 3rd Draft EA Submittal. 100% delivered Jan 9th.
09-Dec-14 ADOT 2nd Review Comments Being Addressed. 100% plans coming in December.
10-Nov-14 Recieved the majority of ADOT's 2nd review comments for the Draft Environmental Assessment. Still awaiting comments from one more section. 100% plans in development.
08-Oct-14 The project status is the same as the previous month.
10-Sep-14 2nd ADOT Review of Environmental Assessment currently taking place. 100% plans in development.
11-Aug-14 2nd ADOT Review of Environmental Assessment currently taking place. 90% plans comments are being addressed.
09-Jul-14 2nd ADOT Review of Environmental Assessment to take place in July. 90% plans comments are being addressed.
10-Jun-14 2nd ADOT Review of Environmental Assessment to take place in June. 90% plans comments are being addressed.
09-May-14 2nd ADOT Review of Environmental Assessment to take place in May. 90% plans comments are being addressed.
07-Apr-14 Status is the same.
10-Mar-14 Initial Environmental Assessment (EA) review completed by ADOT. 90% plans comments are being compiled.
07-Feb-14 Environmental Assessment is under State review. 90% plans comments are being compiled.
14-Jan-14 Environmental Assessment is under both State and Federal review. 90% plans under review.
09-Dec-13 Environmental Assessment is under both State and Federal review. 90% plans to begin review process by Dec. 16th.
08-Oct-13 Continue Environmental Assessment process and finalize bridge pier design. 90% Plans due in November after finalizing bridge design.
07-Aug-13 Continue Environmental Assessment process and finalize bridge pier design.
15-Jul-13 Continue Environmental Assessment process and finalize bridge pier design.
07-Jun-13 Continue Environmental Assessment process and finalize bridge pier design.
09-May-13 Continue Environmental Assessment process and finalize bridge pier design.
Cultural report approved by ADOT.
08-Apr-13 Cultural Report was previously submitted to ADOT for review and staff is awaiting comments.
Environmental Assessment process continues.
11-Mar-13 Staff awaiting comments from Cultural Report that was submitted to ADOT for review.
08-Feb-13 Cultural Report has been submitted to ADOT for review and staff is awaiting comments.
07-Jan-13 - Cultural Report submitted to ADOT for Review
4F concurrence received from Pima County Parks & Recreation Department.
Public Art has been incorporated into the 90% plans.
NOTE: 4F refers to a Department of Transportation Act (DOT Act) of 1966 that requires affected lands to meet the following criteria:
- There is no feasible and prudent alternative to the use of land.
- The action includes all possible planning to minimize harm to the property resulting from use.
03-Dec-12 Phase 1 was completed in September 2012. The status for Phase 2 is:
design plans are at 75% completion with 90% plans coming in early December.