Project #118 - CNG Project

Picture
Location
4004 S. Park Ave.  
Status
In Design  
Total Estimated Project Cost
$13,402,550.00  
Expenditures to Date Through 4/30/2015
$829,025.00  
Estimated date of completion as of 5/7/2014
7/31/2016  
Project Contact
Brian Conte (837-6319)  

View this project on the Projects Map

Description
The project will be completed in two (2) Phases. Overall scope is to replace CNG plant, and install & modify fuel islands at Thomas O. Price Service Center (TOPSC).

Phase I - Design Development Level. This phase establishes a 50% design development document with construction cost estimate. Completed.
Phase II - Installation and modifications of fuel islands and construction of CNG plant. This phase includes completion of the design effort and bid process.  
Additional Info
 
Designation(s)
City of Tucson, Capital Improvement Project  
Last Update
5/14/2015  

Project #118 - Status

06-May-15 Phase II - The construction Contractor has mobilized and equipment is being ordered.
10-Apr-15 Phase II - The project has a construction contract award to D. L. Withers Construction. The project has Mayor and Council approval.
10-Mar-15 Phase II - The project is in the bid award phase. The project has Mayor and Council approval.
13-Feb-15 Phase II - The project is biding. The project has Mayor and Council approval.
07-Jan-15 Phase II - The project is biding. The project has Mayor and Council approval.
09-Dec-14 Phase II - The design is complete and submitted to Development Services for Building Code Plan Check. The project has Mayor and Council approval.
06-Nov-14 The design is complete and submitted to Development Services for Building Code Plan Check. The project has Mayor and Council approval.
02-Oct-14 Status is the same as previous month.
09-Sep-14 Phase II - Completion of the Construction Documents (CD) design level is approved and is moving forward. The project has Mayor and Council approval.
11-Aug-14 Project status is the same as July 2014.
02-Jul-14 Phase II - Completion of the Construction Documents (CD) design level is approved and is moving forward. The project has Mayor and Council approval.
10-Jun-14 The status is the same as April 2014.
07-May-14 Phase II - Completion of the Construction Documents (CD) design level is approved and is moving forward. The project has Mayor and Council approval.
08-Apr-14 Project completion.
07-Mar-14 Phase I - the 50% Design Development (DD) level is complete.
10-Feb-14 Phase I - the Schematic Design (SD) level is complete.
13-Jan-14 No change in status.
06-Dec-13 Phase I - the Schematic Design (SD) level is complete.
07-Nov-13 Phase I - the Schematic Design (SD) level is complete.
08-Oct-13 Phase I - the Schematic Design (SD) level is complete.