Project #119 - 22nd Street: Kino to Tucson Blvd.

Picture
Location
22nd Street: Kino Parkway to Tucson Blvd.  
Status
In Design  
Total Estimated Project Cost
$117,952,000.00  
Expenditures to Date Through 4/30/2015
$38,933,318.00  
Estimated date of completion as of 1/31/2015
10/31/2019  
Project Contact
Joe Chase  

View this project on the Projects Map

Description
This project will widen 22nd Street to three lanes in each direction between Kino Parkway and Tucson Boulevard, and will replace the existing 22nd Street bridge over the Barraza-Aviation Parkway and the Union Pacific Railroad. Design elements include a raised, landscaped median, bike lanes in each direction, a pedestrian bridge within the structure of the new bridge, transit improvements, continuous street lighting, public art integrated into the design of the pedestrian bridge, and a future connection to the Barraza-Aviation Parkway.  
Additional Info
 
Designation(s)
City of Tucson, Street Work, RTA Funded  
Last Update
5/18/2015  

Project #119 - Status

18-May-15 Compiling 75% plan comments.
14-Apr-15 The project status is unchanged for this month.
11-Mar-15 75% complete plans submitted for review. Design complete March 2016.
13-Feb-15 75% complete plans submitted for review. Design complete March 2016.
13-Jan-15 75% complete plans due February 2015. Design complete Mar 2016.
09-Dec-14 75% complete plans due March 2015. Design complete March 2016.
07-Nov-14 75% complete plans due January 2015. Design complete March 2016.
08-Oct-14 40% complete design(no change). Utility design negotiations were renegotiated with Tucson Water (TW). TW's scope of work has changed and expectations finalized finally. We will determine PCRWRD modifications have not been determined yet. The public art scope of work has been finalized.
02-Sep-14 40% complete design(no change). Utility design negotiations were renegotiated with Tucson Water. TW's scope of work has changed and expectations finally finalized . PCRWRD modifications will be determine by TDOT later in the design. The public art scope of work has been finalized.
08-Aug-14 40% complete design(no change). Utility design negotiations were renegotiated with Tucson Water. TW's scope of work has changed and expectations finalized finally. PCRWRD modifications will be determined by staff later in the design. The public art scope of work has been finalized.
15-Jul-14 40% complete design(no change). Utility design negotiations finalized for Tucson Water and PCRWRD modifications. The public art scope of work has been finalized. Meet with UPRR on 7/15/2014 to discuss relocation expectations.
06-Jun-14 40% complete design(no change). Utility design negotiations finalized for Tucson Water and PCRWRD modifications. The public art scope of work has been finalized.
06-May-14 40% complete design.
03-Apr-14 40% Design complete. Design completion date estimated to be summer 2015.
18-Mar-14 Current: 40% Design complete. Design completion date estimated to be summer 2015.
07-Feb-14 Current: 30% Design. Design completion date estimated to be summer 2015.