Project #121 - Chloramination Disinfection Facility at the Tucson Water Reclaimed Plant

Picture
Location
2500 W. Sweetwater Drive  
Status
Completed  
Total Estimated Project Cost
$6,100,000.00  
Expenditures to Date Through 4/30/2015
$6,950,110.85  
Estimated date of completion as of 2/6/2014
4/1/2014  
Project Contact
Howard Woolsoncroft  

View this project on the Projects Map

Description
This project is the construction of nitrogen (ammonia) feed system for the reclaimed water system. The new Pima County Waste Treatment Plant provides secondary effluent nearly void of nitrogen (2 ppm). The old Roger Road Treatment Plant provided secondary effluent with high nitrogen levels (around 29 ppm). The Roger Road Treatment Plant is in the process of being closed.

Chloramination (water treatment) has been ongoing at the Tucson Water Reclaimed Plant from the start. With any level of nitrogen chloramination is the best means of water treatment (consultant study) to insure safe water for irrigation and other uses. The nitrogen level of 2 ppm is too low for proper chloramination so a nitrogen source (ammonia) must be installed. This project will provide the equipment, building, piping, and controls to provide that ammonia.  
Additional Info
 
Designation(s)
City of Tucson  
Last Update
5/12/2015  

Project #121 - Status

04-Apr-14 COMPLETED:
Archeological study
Water line from EW-008 modification. Ready for 30'' riser.
Extraction wells line modification. Ready for 36'' riser.
Building and roof constructed
Ammonia tanks (2) installed with ladders and catwalk
Fire water line (6'') and riser
Mixer installed on pad in Chloramination Control Basin (CCB)
Pipe risers (30'' and 36'') installation at CCB
Chemical sump installation
Set pump skid and installed chemical piping
Electrical wiring and equipment
SCADA logic created and installed in control panel

ACTIVE:
Task 2, Sampling Plan (on going until July 2014)
07-Mar-14 COMPLETED:
Archeological study
Water line from EW-008 modification. Ready for 30'' riser.
Extraction wells line modification. Ready for 36'' riser.
Building shell constructed
Roof
Ammonia tanks (2) installation
Fire water line (6'') and riser
Mixer pad in Chloramination Control Basin (CCB)
Pipe risers (30'' and 36'') installation at CCB
Chemical sump installation
Set pump skid (delivered)

ACTIVE:
Electrical wiring and equipment
SCADA logic being created
Task 2, Sampling Plan (on going until July 2014)
Install chemical piping
Install tank stairs (delivered)
Install mixed (delivered)
06-Feb-14 COMPLETED:
Archeological study
Water line from EW-008 modification. Ready for 30'' riser
Extraction wells line modification. Ready for 36'' riser
Building shell constructed
Roof
Ammonia tanks (2) installation
Fire water line (6”) and riser
Mixer pad in Chloramination Control Basin (CCB)

ACTIVE:
Electrical wiring and equipment
Pipe risers (30'' and 36'') installation at CCB
Chemical sump installation
SCADA logic being created
Task 2, Sampling Plan (on going until July 2014)