Location
Houghton south of Golf Links  
Status
Completed  
Total Estimated Project Cost
$29,000,000.00  
Expenditures to Date Through 4/30/2015
$20,855,910.00  
Estimated date of completion as of 6/3/2014
6/30/2014  
Project Contact
MJ Dillard  

View this project on the Projects Map

Description
This project is part of the RTA Houghton Corridor Improvements that will expand travel capacity and safety in this key north-south regional corridor to accommodate the 2030 traffic demands. Specifically, this project will replace four miles of the existing two-lane roadway with a new six-lane divided desert parkway. The roadway work will include improved intersections with dual left turn lanes, exclusive right turn lanes and upgraded traffic signals; rubberized asphalt for noise mitigation; native landscaping with water harvesting; improved multi-modal access by adding bike lanes on and off the roadway, improving ADA-accessibility and adding sidewalks and multi-use paths, and include bus pullouts and transit options; upgraded drainage and add all-weather crossings, landscaping that enhances the scenic corridor and utilizes water harvesting and incorporates native plants; implement Wildlife-sensitive design features; and bring in Public Art.  
Additional Info
 
Designation(s)
City of Tucson, Street Work, RTA Funded  
Last Update
5/15/2015  

Project #122 - Status

15-Jul-14 Construction completed, landscape establishment period (2 years) started.
02-Jun-14 Construction completion expected this month.
06-May-14 Wrapping up final rubberized asphalt placement, striping and landscaping.
01-Apr-14 Completing the final landscape installation and rubberized asphalt installation.
18-Mar-14 No change.
07-Feb-14 Completing the final construction phases of this project, with an anticipated final completion in May of this year.