Current Projects

Project #124 - Supervisory Control and Data Acquisition

Picture
Location
Tucson Water Headquarters  
Status
In Planning  
Total Estimated Project Cost
$17,673,000.00  
Expenditures to Date Through 4/30/2015
$1,951,266.37  
Estimated date of completion as of 2/10/2014
6/30/2019  
Project Contact
 

View this project on the Projects Map

Description
Tucson Water’s SCADA system controls processes such as water pressures, flows, reservoir levels and energy use at over 350 sites across the entire delivery area. The 12 gigabytes of data it produces annually is used for trouble shooting water system issues, planning, cost analysis and regulatory compliance. The SCADA system is essential to Tucson Water’s operations and its upgrade critical to the future viability and reliability of the services Tucson Water provides. Many of SCADA’s components are at the end of their life-cycle and must be replaced. Tucson Water has undertaken a series of projects to replace and upgrade the system.  
Additional Info
 
Designation(s)
City of Tucson, Capital Improvement Project  
Last Update
5/12/2015  

Project #124 - Status

11-May-15 Human Machine Interface (HMI) - Development of design criteria into specifications for hardware and software underway.
Reviewing HMI hardware draft design.
Design/construction for three remaining pilot sites is continuing.
Long term System Integration (SI) contract negotiations underway.
Telecommunications coordination with City staff underway.

10-Apr-15 Human Machine Interface (HMI) - Development of design criteria into specifications for hardware and software underway.
Design/construction for three remaining pilot sites is continuing.
Long term System Integration (SI) RFP Phase 2 evaluation complete.
Telecommunications coordination with City staff underway.
11-Mar-15 Human Machine Interface (HMI) first steps meetings underway.
First pilot site construction complete. Testing period TBD.
Design/construction for three remaining pilot sites is continuing.
Long term System Integration (SI) RFP Phase 2 responses being evaluated.
13-Feb-15 Human Machine Interface (HMI) kick-off meting and first steps discussed.
First pilot site construction substantially complete pending testing.
Design/construction for three remaining pilot sites is continuing.
Long term System Integration (SI) RFP Phase one complete.
Long term System Integration (SI) RFP Phase 2 issued.
13-Feb-15 Human Machine Interface (HMI) kick-off meting and first steps discussed.
First pilot site construction substantially complete pending testing.
Design/construction for three remaining pilot sites is continuing.
Long term System Integration (SI) RFP Phase one complete.
Long term System Integration (SI) RFP Phase 2 issued.
10-Jan-15 Human Machine Interface (HMI) kick-off meting and first steps discussed.
First pilot site design construction and commissioning activity underway.
Design for three remaining pilot sites is continuing.
Long term System Integration (SI) RFP Pre-Bid meeting held
Long term System Integration (SI) RFP Phase 2 issuance pending
05-Dec-14 Human Machine Interface (HMI) Contract awarded.
First pilot site design construction and commissioning activity underway.
Design for three remaining pilot sites is continuing.
Long term System Integration (SI) RFP Phase 1 issued.
Long term System Integration (SI) RFP Phase 2 in draft review.
07-Nov-14 Human Machine Interface (HMI) Contract awarded.
First Pilot site design construction and commissioning activity underway.
Design for three remaining Pilot sites is continuing.
Revised Wide Area Network documentation received.
Long term System Integration (SI) QVL to be issued.
Long term System Integration (SI) RFP draft revision in review at City Hall.
08-Oct-14 Human Machine Interface (HMI) Contract Negotiations underway.
Design for the remaining four Pilot sites is continuing.
First Pilot site design construction activity underway.
Long term System Integration (SI) RFP draft revision in review at City Hall.
08-Sep-14 Human Machine Interface (HMI) Contract Negotiations underway.
Design for the remaining four Pilot sites is continuing.
First Pilot site design construction activity underway.
Long term System Integration (SI) RFP draft revision in review at City Hall.
08-Aug-14 Human Machine Interface (HMI) Contract Negotiations underway.
Design for the remaining four Pilot sites is continuing.
First Pilot site design construction activity underway.
Long term System Integration (SI) RFP draft revision continues.
14-Jul-14 Human Machine Interface (HMI) Contract Negotiations begun
Design for the remaining four Pilot sites is continuing.
First Pilot site design construction activity underway.
Programmable Logic Controller (PLC) radio communication testing performed on current system.
Long term System Integration (SI) RFP draft revision continues.
06-Jun-14 Human Machine Interface (HMI) RFP Notice of Intent sent
Design for the remaining four Pilot sites is continuing.
First Pilot site Station Control Panel Factory Acceptance Testing Completed.
First Pilot site design construction activity underway.
Wide Area Network meeting resulted in revised documentation criteria.
Methods and Standards documentation continuing.
Programmable Logic Controller (PLC) radio communication prototype test results received.
Current HMI development system hardware to be received and software installed.
Long term System Integration (SI) RFP draft revision continues.
06-May-14 Human Machine Interface (HMI) RFP Phase Two underway
Design for the remaining four Pilot sites is continuing.
First Pilot site Station Control Panel was submitted for build.
First Pilot site design was submitted for construction.
Wide Area Network Phase 1 (documentation and testing) is continuing.
Methods and Standards documentation continuing.
Programmable Logic Controller (PLC) radio communication lab testing continuing.
Long term System Integration (SI) RFP draft is under revision by staff.
11-Apr-14 No status provided.
20-Mar-14 Human Machine Interface (HMI) software demos were conducted.
Design for the remaining four Pilot sites is continuing.
First Pilot site Station Control Panel was submitted for build.
First Pilot site design was submitted for construction.
Wide Area Network Phase 1 (documentation and testing) has begun.
Methods and Standards are being documented.
Standard prototype Programmable Logic Controller (PLC) and radios being tested in lab.
Long term System Integration (SI) RFP draft is under revision by staff.
10-Feb-14 Human Machine Interface (HMI) software RFP submission selection is in process.
Design for the first five Pilot sites is underway by staff.
Wide Area Network documentation and design to be performed under direction of City IT using -State contract.
Radio communication documentation and evaluation being performed under direction of Communications Engineering.
Methods and Standards are being documented.
Long term System Integration RFP is being drafted.

Project #124 - Pictures

There are no pictures to display

Project #124 - Attachments

There are no attachments to display