Project #132 - Los Reales Landfill

Picture
Location
Los Reales/Craycroft  
Status
Under Construction  
Total Estimated Project Cost
$7,771,000.00  
Expenditures to Date Through 4/30/2015
$3,534,709.09  
Estimated date of completion as of 3/10/2015
5/20/2015  
Project Contact
Martin Dupont (837-4004)  

Description
Los Reales Landfill Phase I Improvements (New Entry, New Administration/Crew Building, New CABOP, New Scales and Scale Houses, and New Wheel Wash).  
Additional Info
 
Designation(s)
City of Tucson, Capital Improvement Project  
Last Update
5/18/2015  

Project #132 - Status

18-May-15 No status report provided.
10-Apr-15 CABOP, Scale Houses, and Administration building are all nearing completion. Delays encountered with TEP Service pushed paving activities to begin on March 31, 2015 from March 16, 2015. Power up of buildings is expected to occur on May 20, 2015.
10-Mar-15 CABOP, Scale Houses, and Administration building are all nearing completion. Roadway’s and parking lots are scheduled to be paved beginning March16, 2015. Power up of buildings is expected to occur on May 20, 2015.
13-Feb-15 High roof structure at CABOP is nearing completion. Scale house masonry walls are complete and high roof is under construction. Administration metal building arrived on January 23, 2015, the building framing is being erected. Paving activities are scheduled to begin February 16, 2015.
12-Jan-15 High roof structure at CABOP is nearing completion. Scale house masonry walls near completion and high roof is under construction. Column footings at Admin building are poured and underground utilities are in. Metal building package is expected to arrive in late January.
09-Dec-14 CABOP slab poured high roof structure under construction. Scale house masonry walls going up, canopy columns poured, and underground utilities are in. Final water main connections are near completion. Column footings at Admin building are poured and underground utilities are going in. Metal building package is expected to arrive in late January.
05-Nov-14 Scale house stem walls are formed; excavation for water line along the north entrance road is in progress; underground electrical at scales and CABOP; underground plumbing there complete; sewer complete except for final tie-in.
07-Oct-14 Excavation of buildings pads and underground utility trenching and installation is ongoing. Harvesting of native plants is completed. Trenching of building foundations and utility rough-in is underway.
09-Sep-14 Excavation of buildings pads and underground utility trenching is underway. Native plants were harvested and donated per City and State Statute.
07-Aug-14 Building and grading permits issued July 2014, Notice to proceed to contractor issued for August 4, 2014. Construction trailer was placed the week of July 28, 2014, and contractor mobilized on August 4, 2014. First construction site meeting was held on August 5, 2014.