Project #72 - 22nd Street Corridor Planning Study, I-10 to Kino Parkway

Picture
Location
22nd Street, I-10 to Kino Parkway  
Status
On Hold  
Total Estimated Project Cost
$0.00  
Expenditures to Date Through 12/31/1969
$0.00  
Estimated date of completion as of 4/1/2014
12/31/2023  
Project Contact
Janice Cuaron  

Description
This project will widen 22nd Street from four (4) to six (6) lanes, with a raised landscaped median, grade separation at the Union Pacific Railroad Nogales tracks, drainage improvements, bicycle lanes, transit improvements, street lighting, sidewalks and public art.  
Additional Info
The roadway design and land use concepts along this corridor will improve motorized and non-motorized safety and mobility, reduce vehicular congestion, and enhance existing neighborhoods adjacent to 22nd Street.  
Designation(s)
City of Tucson, Street Work  
Last Update
5/18/2015  

Project #72 - Status

06-May-15 The planning phase for this project originally started in 2008. A citizen's committee was established to identify a preferred alignment and to assist with design. The planning phase was halted in late 2009 due to the contentious nature of the project, and the atempt by the citizen committee to derail the process.

10-Apr-15 The planning phase for this project originally started in 2008. A citizen's committee was established to identify a preferred alignment and to assist with design. The planning phase was halted in late 2009 due to the contentious nature of the project, and the atempt by the citizen committee to derail the process.

11-Mar-15 The planning phase for this project originally started in 2008. A citizen's committee was established to identify a preferred alignment and to assist with design. The planning phase was halted in late 2009 due to the contentious nature of the project, and the atempt by the citizen committee to derail the process.

13-Feb-15 The planning phase for this project originally started in 2008. A citizen's committee was established to identify a preferred alignment and to assist with design. The planning phase was halted in late 2009 due to the contentious nature of the project, and the atempt by the citizen committee to derail the process.

08-Jan-15 The planning phase for this project originally started in 2008. A citizen's committee was established to identify a preferred alignment and to assist with design. The planning phase was halted in late 2009 due to the contentious nature of the project, and the attempt by the citizen committee to derail the process.
05-Dec-14 The planning phase for this project originally started in 2008. A citizen's committee was established to identify a preferred alignment and to assist with design. The planning phase was halted in late 2009 due to the contentious nature of the project, and the attempt by the citizen committee to derail the process.
05-Nov-14 The planning phase for this project originally started in 2008. A citizen's committee was established to identify a preferred alignment and to assist with design. The planning phase was halted in late 2009 due to the contentious nature of the project, and the attempt by the citizen committee to derail the process.
08-Oct-14 The planning phase for this project originally started in 2008. A citizen's committee was established to identify a preferred alignment and to assist with design. The planning phase was halted in late 2009 due to the contentious nature of the project, and the attempt by the citizen committee to derail the process.
04-Sep-14 The planning phase for this project originally started in 2008. A citizen's committee was established to identify a preferred alignment and to assist with design. The planning phase was halted in late 2009 due to the contentious nature of the project, and the attempt by the citizen committee to derail the process.
07-Aug-14 The planning phase for this project originally started in 2008. A citizen's committee was established to identify a preferred alignment and to assist with design. The planning phase was halted in late 2009 due to the contentious nature of the project, and the attempt by the citizen committee to derail the process.
05-Aug-14 The planning phase for this project originally started in 2008. A citizen's committee was established to identify a preferred alignment and to assist with design. The planning phase was halted in late 2009 due to the contentious nature of the project, and the attempt by the citizen committee to derail the process.
06-May-14 The planning phase for this project originally started in 2008. A citizen's committee was established to identify a preferred alignment and to assist with design. The planning phase was halted in late 2009 due to the issues and concern brought forth from the citizen's committee.

Project #72 - Pictures

There are no pictures to display

Project #72 - Attachments

There are no attachments to display