Project #82 - Downtown Links - Barraza-Aviation

Picture
Location
north of the railroad tracks from Barraza-Aviation to the I-10 frontage road with a reroute of 6th S  
Status
In Design  
Total Estimated Project Cost
$84,674,000.00  
Expenditures to Date Through 4/30/2015
$33,358,222.00  
Estimated date of completion as of 1/31/2013
12/31/2019  
Project Contact
Sam Credio (837-6641)  

Description
The project will be a modest, four-lane roadway north of the Union Pacific railroad tracks that will connect Barraza-Aviation Parkway to 22nd Street and I-10, offering an alternate access to Downtown, plus new underpass with the Union Pacific railroad. The project is divided into four separate construction phases.  
Additional Info
 
Designation(s)
City of Tucson, Street Work, Streetscape Work  
Last Update
5/15/2015  

Project #82 - Status

12-May-15 In the process of finalizing 100% design package. This includes plans, specification and estimate. Ongoing Coordination with the Union Pacific Railroad (UPRR), utility companies and Citizens Advisory Committee (CAC).

10-Apr-15 There is no change in the status for this project.
09-Mar-15 Phase III design will be 100% complete by April. TDOT continues to work with the Union Pacific Railroad (UPRR) and the major utility companies on final design approval. Some utility relocations will begin in late spring/early summer. Real Estate is working on the final property acquisitions to be completed by this summer 2015, with demolitions to follow. Phase II environmental reports for properties will begin in April.
13-Feb-15 No change in status.

13-Jan-15 TDOT has completed its review of the 90% plans for Downtown Links Phase III from Church Ave. to Broadway. The design consultant is now actively working towards 100% design completion. Real Estate staff is actively working on the acquisition of remaining properties needed for the corridor. Development of the artists' concepts for the retaining walls is ongoing. Utility relocations will begin in March 2015.
10-Dec-14 Phase III from Church Ave. to Broadway is at 90% design completion and progressing to 100% by early 2015. Plan review by City staff, utilities and Union Pacific is in progress. Real Estate staff is actively working on the acquisition of remaining properties needed for the corridor. Development of the artists' concepts for the retaining walls is ongoing. ADEQ is relocating several monitoring wells that are within the Downtown Links corridor including those that were removed due to the 8th Street Drainage project.
06-Nov-14 Phase III from Church Ave. to Broadway is at 90% design completion and progressing to 100% by early 2015. Plan review by City staff, utilities and Union Pacific is in progress. Real Estate staff is actively working on the acquisition of remaining properties needed for the corridor. Development of the artists' concepts for the retaining walls is ongoing. ADEQ is relocating several monitoring wells that are within the Downtown Links corridor including those that were removed due to the 8th Street Drainage project.
03-Oct-14 Phase III from Church Ave. to Broadway is at 90% design completion and progressing to 100% by January. Plan review by City staff is in progress. TDOT worked with ADOT to complete demolition of three warehouses in mid September. Real Estate staff is working on the acquisition of remaining properties. ADEQ is relocating several monitoring wells that are within the Downtown Links corridor.
03-Sep-14 Phase III from Church Ave. to Broadway will be at 90% design completion by September and progressing to 100% by January. TDOT staff is working with ADOT on the demolition of three warehouses which will be complete by mid September. Real Estate staff is working on the acquisition of remaining properties. ADEQ is relocating several monitoring wells that are within the Downtown Links corridor.
06-Aug-14 Phase III from Church Ave. to Broadway is at 75% design completion and progressing to 90%. TDOT staff is working with ADOT on the demolition of three warehouses to begin in late August. Real Estate staff is working on the acquisition of remaining properties. DSD and Planning staff is working on the UOD overlay zone for the corridor as well as other downtown areas. ADEQ is relocating several monitoring wells that are in the Downtown Links corridor.
07-Jul-14 Phase III from Church Ave. to Broadway is at 75% design completion. TDOT staff is working with ADOT on the demolition of three warehouses while preserving others. Real Estate staff is working on the acquisition of remaining properties. DSD and Planning staff is working on the UOD overlay zone for the corridor as well as other downtown areas.
03-Jun-14 Phase III from Church Ave. to Broadway is at 75% design completion. TDOT staff is working with ADOT on the demolition of three warehouses while preserving others. Real Estate staff is working on the acquisition of remaining properties. DSD and Planning staff is working on the UOD overlay zone for the corridor as well as other downtown areas.
05-May-14 Phase II: St. Mary's Road Improvements was just completed in May. Phase III from Church Ave. to Broadway is at 75% design.
01-Apr-14 No changes.
07-Mar-14 Phase II St. Mary's Roadway improvements will be fully complete by April. Phase III Church to Broadway segment is at 75% design. Remaining property acquisitions in process. Three ADOT warehouses will be demolished by June 2014.
04-Feb-14 No change.
08-Jan-14 St. Mary's Roadway improvements are wrapping up and will reach ''substantial completion by end of January. The final 2'' of rubberized asphalt will be installed in March when temperatures are above 65 degrees.

Phase III is nearing 90% design completion. Remaining property acquisitions in process.

Phase II: St. Mary's Roadway Improvements, March 2014

Phase III: Church to Broadway, design to be completed by January 2015 and go to construction in late 2015.
02-Dec-13 Phase II: St. Mary's Roadway is under construction and 90% complete and estimated completion date of January 2014.
Phase III: Church to Broadway is under design and 75% complete. Full design to be completed by January 2015.
08-Nov-13 Phase II: St. Marys Roadway is under construction and 85% complete and estimated completion date of January 2014.

Phase III: Church to Broadway is under design and 75% complete. Full design to be completed by January 2015.
07-Oct-13 Phase II: St. Marys Roadway Improvements are 75% complete and still on schedule

Phase III: 6th Street to Broadway at 75% design completion. RTA recently approved funding for remaining property acquisitions and design scope for Phase III.
09-Sep-13 Phase II: St. Marys Road is under construction and 70% complete.

Phase III: 6th Street and Links Ave. is in design at almost 75% complete.

The 6th Street/6th Avenue signal upgrade is under construction and 90% complete.
01-Aug-13 St. Marys construction is 65% complete and on schedule for full completion in January 2014.

Stone Transmission building was demolished in late July. The site is being cleaned, leveled, and completed with a gravel surface by mid August. Parkwise will manage the site as parking for the next few years.
01-Jul-13 St. Marys construction is 55% complete and on schedule for full completion in January 2014.

Stone Transmission building will be demolished on July 8th. The site will be cleaned, leveled, and completed with a gravel surface by end of July.
04-Jun-13 --the St. Marys roadway construction is 45% complete. The section between Granada and Church will re-open to through-traffic starting June 10th

--the Stone Transmission building will be demolished in June, pending removal of oil liquids abandoned on site.

--A Citizens Advisory Committee CAC) bike/pedestrian subcommittee was formed to help identify remaining issues with bike and pedestrian connectivity for design of Phase III: Church to Broadway
06-May-13 St. Marys construction is 30% complete and still on schedule for full completion January 2014. The roadway is temporarily closed between Granada and Church to install a 90" storm drain. The roadway will reopen in early June.

The Citizens Advisory COmmittee (CAC) Deck Park Subcommittee adopted a design concept for the deck park which will be presented to the full CAC on May 13th. City staff will review in the coming weeks for further consideration and approval.

Phase III from Church to Broadway still at 30% design due to ongoing structural and environmental reports. Will reach 75% design by August.

Demolition of the Stone Transmission building (529 N. Stone) will take place this summer. A pre-bid meeting is scheduled for May 8th.

No further property acquisitions or demos will occur until funding is approved by RTA in September.
01-Apr-13 St. Marys construction is at 20% completion. Work continues on drainage and utilities.
Phases III and IV still at 30% completion. Coordinating with Union Pacific Railroad on rail bridge structural design.
04-Mar-13 St. Marys Improvements 10% complete. Work is continuing on drainage and utilities.
Phases III and IV still at 30% completion. Coordinating with Union Pacific Railroad on rail bridge structural design.
04-Feb-13 St. Marys is under construction and scheduled for completion in January 2014. Crews opened up the road to 4 lanes for the duration of the Gem Show, ending Feb 17th.

The 6th Street: Church to Broadway section is in design. A Citzens Advisory Committee meeting was held last month, and further direction was provided to the design team regarding key issues. Remaining property acquisitions will be initiated in the next 6-12 months.
02-Jan-13 The St. Marys section from I-10 to Church Ave under construction.
Phase III in design and still at 30%. Currently working on environmental reports and property acquistions. The Lucky Street warehouse was demo-ed and cleared in December.
03-Dec-12 The St. Marys section from I-10 to Church Ave. broke ground on November 5th and is scheduled for completion in January 2014. Borderland Construction is the contractor.

Phase III and IV from Church Ave. to Broadway is in design at currently at 30%. In the process of doing environmental and geotechnical reporting.

The Urban Overlay District is on hold until January after the Office of the City Manager has reviewed the draft document and coordinated with parking plans.
01-Oct-12 St. Marys improvements to start construction November 5th by Borderland Construction. 12 to 15-month project.

Beginning design work on segment from 6th Street underpass to Broadway. 24-month process to go from 30% to 100% design completion.
05-Sep-12 Phase II St. Marys Improvements low bid awarded to Borderland Construction. Estimated construction start date is mid October.
Phase III 6th Street Underpass to Broadway at 30% design. The Citizen Advisory Committee will be convened in late September to re-initiate the design process.
08-Aug-12 St. Marys segment went out to bid in early July. Bid openings on August 16th. Construction to start in mid September.
6th Street and Links Avenue plans at 30% and to begin design in late August. CAC meeting scheduled for August 20th.
09-Jul-12 --Phase I 8th Street drainage segment completed
--Phase II St. Marys improvements went out to bid in late June
--Phase III 6th Street Underpass and Links Avenue received RTA funding to complete design. Design efforts begin in August and full design will take a minimum two years.
07-Jun-12 8th Street Drainage is 100% complete.
St. Marys segment going out to bid in June pending plan approval by Tucson Water.
The middle segment still at 30% design completion. Seeking additional RTA funding to complete design. Will go to RTA Board for discussion on June 14th.
01-May-12 8th Street Drainage phase is 97% complete. Fully complete by mid May.
St. Marys segment will go out to bid in May, pending sewer and water approvals.
RTA Value Analysis completed for middle segment. TDOT is seeking funds from RTA to re- initiate design for middle segment.
02-Apr-12 8th Street drainage project 90% complete. Final completion in early May.
St. Marys portion will go out to bid in late March. Construction to start in early June.
Just completed a Value Analysis with the RTA on the middle segments. Will begin design pending RTA funding approval in April.
06-Mar-12 8th Street drainage in 70% complete and on schedule to be completed in early April.

St. Marys portion will go out to bid in late March. Construction to start in early June.

Just completed a Value Analysis with the RTA on the middle segments. Will begin design pending RTA funding approval in April.
08-Feb-12 8th Street drainage construction is 65% complete.
St. Marys segment will go out to bid in March.
Will conduct a Value Analysis with the Regional Transportation Authority the week of Feb 13-17 for the middle segments.
03-Jan-12 8th Street drainage project is 35% complete and on schedule. Some phasing changes due to working around business access needs and schedule adherence.
06-Dec-11 The 8th Street drainage portion of the project is nearing 25% completion and on schedule.
02-Nov-11 Major trenching and culvert installation on 7th Street currently in progress. Total drainage project is 10% complete. Two buildings on 6th Avenue and on 8th Street have been demolished and site is clean.
04-Oct-11 Borderland Construction construction effort started October 3rd. First major trenching on 7th Street to begin October 24th. There will be re-striping of 6th Ave from 6th St to 7th St to two-way travel, and a four-way stop at 6th Ave/7th St.
Demolition of two vacant buildings at 220 E. 8th Street and 320 N. 6th Ave to begin the week of October 10th. Land will be used for construction staging and some parking.
07-Sep-11 8th Street Drainage contract awarded to Borderland Co. Construction and scheduled to begin late September.
St. Marys segment in design with 100% completion planned for end of September.
Middle segment at 30% design and on hold.
04-Aug-11 The 8th Street Drainage plans are $100% complete. Went out to bid on July 11th and bid openings are scheduled for August 12th. Construction to start in mid September.The Urban Overlay District (UOD) is currently under review by DSD. A traffic impact analysis (TIA) draft is completed and under review.
07-Jul-11 The 8th Street Drainage project design is 100% complete. It will go out to bid in early August due to delays with Pima County Waste Water review and permitting. The St. Marys segment will go out to bid in September.
07-Apr-11 inalizing design and permitting for the 8th Street Drainage improvements. TDOT has secured $9 million in RTA funds for the project which will go out to bid in May. The St. Marys segment design is 99% complete. The project will go out to bid in late summer pending RTA funding. Phases 3 and 4 design for the rest of the corridor is at 30%. Further design is on hold due to RTA funding shortages.
07-Feb-11 Still finalizing plans for the 8th Street Drainage improvements and the St. Marys segment. TDOT has secured $9 million in RTA funds for the 8th Street drainage improvements. Funding for the St. Marys segment is still pending.
05-Jan-11 The St. Marys segment will go out to bid in mid 2011, pending RTA funding approval. Final design of the middle segments will continue, pending RTA funding approval.
03-Dec-10 The 8th Street drainage and St. Marys segments are nearing 100% design completion. The 8th Street drainage segment will go out to bid in early 2011 in coordination with the modern street improvements. The St. Marys segment will go out to bid in early/mid 2011. Design continuing to advance beyond 30% design on the other segments.
02-Nov-10 The 8th Street drainage and St. Marys plans are now at 95% completion.
Both will go out to bid in early 2011.
08-Oct-10 Estimated completion dates:
Phase I- 8th Street Drainage: late 2011 (drainage plans 90% complete)
Phase II- St. Mary's from I-10 to Church: early 2012 (design plans 90% complete)
Phases III and IV- Railroad Underpass and Links: 2016 (Period 3 per RTA plan) (design plans 30% complete)
06-Aug-10 Currently the project has Finished 30% overall plan set for Downtown Links. Since then the project has been divided up into segments. 90% design plans for the St. Marys Segment (I-10 to Church Avenue), HDR (design consultant)is addressing 75% Comments from the City of Tucson and Utilities on the 8th Street Drainage.
St. Marys segment will go out to bid in late 2010. The 8th Street Drainage improvements will go out to bid in early 2011 in coordination with the Modern Streetcar improvements on 8th Street. HDR continuing to advance design on the other segments.
02-Jul-10 Comments from the City of Tucson and Utilities on the 8th Street Drainage Segment. The Final Plan Specification & Estimate package to be constructed with the Streetcar Line Segment 3 with construction schedule to be determined. HDR, the design contractor is scoping the next two final design segments (6th Street Underpass and Links Avenue). Links Avenue Segment will start Final Design Fall/Winter 2010 and will take 24 months to complete. 6th Street Segment will start Final Design Fall/Winter 2010 and will take 24 Months to complete.
07-May-10 Currently the project has Finished preliminary design plans (30% complete) for the entire route, and the project has been divided into four design segments.
St. Marys Segment currently developing 90% Plans for submittal by the end of May of 2010 with Final PS&E package available for construction Summer/Fall 2010. 8th Street Drainage submitted 75% Plans and waiting for comments.
02-Apr-10 Currently the project has Finished preliminary design plans (30% complete) for the entire route, and the project has been divided into four design segments.
St. Marys Segment submitted 75% Plans in February 2010 with Final Plan Specifications & Estimate (PS&E) package available for construction summer 2010. 8th Street Drainage currently developing 75% Plans for submittal by end of March 2010 with Final PS&E package to be constructed with the Streetcar Line Segment 3 with construction schedule to be determined.
Links Avenue Segment will start Final Design Summer 2010 and will take 24 months to complete. 6th Street Segment will start Final Design Summer 2010 and will take 24 Months to complete.

Project #82 - Pictures

21-Nov-11 Large drainage project is underway.

Project #82 - Attachments

21-Nov-11 Map overview This overview provides a 20,000 foot view of the new route connecting Aviation, Broadway, and 6th St access to the I-10 freeway.
30-Sep-11 8th Street Drainage Improvement Project News Release: "On Monday, October 3, 2011, crews will begin construction.....", read all about it.