Campbell Avenue - Broadway to Third Street Resurfacing Project: Updated Schedule

Crews from Southern Arizona Paving and Construction Co., under contract with the City of Tucson Department of Transportation (TDOT), are scheduled to complete the milling (removing asphalt) and repaving work on Campbell Avenue from Broadway to Third Street during the week of Monday, January 19, 2015.

Crews will mill the roadway on Monday, January 19, 2015 and repave Campbell Avenue on Tuesday, January 20, 2015 and Wednesday January 21, 2015. To minimize impacts to the adjacent residents, work hours will be 7 a.m. to 5 p.m. 

Once the paving work is complete, crews will begin utility adjustments by raising the manhole covers and water main covers flush with the new asphalt. The utility adjustments will begin Monday, January 26, 2015 and are scheduled to be complete on Thursday February 5, 2015. Crews will work Monday through Thursday, 7 a.m. to 5 p.m. During this work, concrete must cure for 24 hours prior to reopening a travel lane to motor vehicles. 

This pavement improvement project is part of the $100 million, five-year street bond program – Road Recovery. The Road Recovery program is funded by voter-approved bonds.

Residential and business access will be maintained at all times during the project, except for when heavy equipment is directly in front of a driveway.  At least two lanes of travel in each direction will be maintained during this work. Please obey all traffic control signs and watch for construction personnel and equipment in these work areas. The schedule is subject to change due to equipment malfunction or inclement weather. 

More information on the Road Recovery Program can be found at www.tucsonaz.gov/street-bonds or by calling (520) 837-6686.