Campbell Avenue - Duvall Vista to Cochise Vista Resurfacing Project

On Thursday, March 5, 2015, crews from the Ashton Company, under contract with the City of Tucson Department of Transportation (TDOT), will begin work to improve the pavement conditions on Campbell Avenue between Duvall Vista and Cochise Vista near Kino Parkway and 36th Street. 

Crews will begin the project by milling (removing asphalt) and crack sealing the remaining roadway. On Friday, March 6, 2015, crews will patch the roadway and then repave the 1,200-foot-long section of milled roadway with new asphalt. 
Work hours will be 7 a.m. to 4 p.m. both days. The roadway will be closed to through traffic during the work. Local traffic will be allowed to access the residences within the construction zone. 

Utility adjustments, shoulder work and striping will take place during the week of Monday, March 9, 2015 and is scheduled to take three days to complete.

Please obey all traffic control signs and watch for construction personnel and equipment in the work area. The schedule is subject to change due to equipment malfunction or inclement weather.