Crack Seal/Fog Seal Work - Prop 101 Tucson Delivers

Crews from VSS International, under contract with the City of Tucson Department of Transportation and Mobility (DTM), are scheduled to begin crack seal work on various roadway segments throughout the City. The roadway improvements are associated with the voter-approved Prop 101 Tucson Delivers Better Streets Program.

During the two-month-long crack seal roadway improvement project, work hours will be from 7 a.m. to 4 p.m., Monday through Friday. The dates and locations where the improvements will take place in the first two weeks of the program are:

Tuesday, February 22, 2022 through March 8, 2022

Nogales Highway – Valencia Road to Los Reales Road
Wilmot Road and Valencia Road intersection
Littletown Road and Valencia Road intersection
Nogales Highway – Drexel Road to Valencia Road
Drexel Road and Nogales Highway intersection
Bilby Road and Nogales Highway intersection
Irvington Road – Benson Highway to Park Avenue/Mountain Avenue
Irvington Road – Mountain Avenue to Nogales Highway
Benson Highway – Irvington Road to Interstate 10
Campbell Avenue and Benson Highway intersection

Crews are scheduled to return to these roadways following the crack seal work to fog seal all roadways associated with this program. Fog sealing is the application of a thin layer of asphalt emulsion that helps cover small roadway imperfections, cracks or other small voids and seals the existing asphalt to preserve and rejuvenate the asphalt.

During this work travel lane restrictions will be in place where crews are working. At least one lane of travel will be maintained in both directions. The traveling public can expect delays when driving in these work areas. Please obey all traffic control signs and watch for construction personnel and equipment in the work area. This schedule is subject to change due to inclement weather or unforeseen circumstances.

Tucson Delivers Better Streets is a $100 million improvement program made possible by Tucson voters who approved a half-cent sales tax increase in May 2017. Thank you in advance for your cooperation as we work to improve the quality and safety of your City streets. For more information on the Tucson Delivers Better Streets Program, visit https://www.tucsonaz.gov/tucsondelivers

TUCSON DELIVERS BETTER STREETS PROP 101

SELLO DE GRIETA/SELLO DE NIEBLA PROGRAMADO PARA COMENZAR

    

Las cuadrillas de VSS International, bajo contrato con el Departamento de Transporte y Movilidad (DTM) de la Ciudad de Tucson, están programadas para comenzar el trabajo de sellado de grietas en varios segmentos de carreteras en toda la Ciudad. Las mejoras viales están asociadas con el programa Prop 101 Tucson Delivers Better Streets aprobado por los votantes.

Durante los dos meses de duración del proyecto de sellado de grietas en las carreteras, el horario de trabajo será de 7 a.m. a 4 p.m., de lunes a viernes. Las fechas y lugares donde se realizarán las mejoras en las dos primeras semanas del programa son:

Martes 22 de febrero hasta 8 de marzo del 2022

Nogales Highway – Valencia Road a Los Reales Road
Wilmot Road y Valencia Road intersection
Littletown Road y Valencia Road intersection
Nogales Highway – Drexel Road a Valencia Road
Drexel Road y Nogales Highway intersection
Bilby Road y Nogales Highway intersection
Irvington Road – Benson Highway a Park Avenue/Mountain Avenue
Irvington Road – Mountain Avenue a Nogales Highway
Benson Highway – Irvington Road a Interstate 10
Campbell Avenue y Benson Highway intersection

Está previsto que las cuadrillas regresen a estas carreteras después del trabajo de sellado de grietas para sellar todas las carreteras asociadas con este programa. El sellado con niebla es la aplicación de una capa delgada de emulsión asfáltica que ayuda a cubrir pequeñas imperfecciones, grietas u otros pequeños huecos en la carretera y sella el asfalto existente para preservar y rejuvenecer el asfalto.

Durante este trabajo, se aplicarán restricciones de carriles de circulación donde las cuadrillas estén trabajando. Se mantendrá al menos un carril de circulación en ambas direcciones. El público que viaja puede esperar retrasos al conducir en estas áreas de trabajo. Obedezca todas las señales de control de tráfico y esté atento al personal y el equipo de construcción en el área de trabajo. Este horario está sujeto a cambios debido a las inclemencias del tiempo o circunstancias imprevistas.

Tucson Delivers Better Streets es un programa de mejora de $100 millones que fue posible gracias a los votantes de Tucson que aprobaron un aumento de impuestos sobre las ventas de medio centavo en mayo de 2017. Gracias de antemano por su cooperación mientras trabajamos para mejorar la calidad y la seguridad de las calles de su ciudad. Para obtener más información sobre el programa Tucson Delivers Better Streets, visite: https://www.tucsonaz.gov/tucsondelivers