Old Spanish Trail - Houghton Road to 22nd Street Reconstruction

On Monday, March 28, 2016 Southern Arizona Paving, under contract with the City of Tucson Department of Transportation TDOT, is scheduled to begin work on Old Spanish Trail from Houghton Road to 22nd Street.

Old Spanish Trail will be reconstructed in four phases. One lane of travel in each direction will be maintained during the work.

  • Phase I – Remove asphalt, reconstruct subgrade and repave north side (westbound) of Old Spanish Trail.
  • Phase II – Remove asphalt, reconstruct subgrade and repave center section of Old Spanish Trail.
  • Phase III – Remove asphalt, reconstruct subgrade and repave south side (eastbound) of Old Spanish Trail.
  • Phase IV – Repave final layer of asphalt on Old Spanish Trail from Houghton to 22nd Street.

Crews will work on Old Spanish Trail Monday through Friday, from 6 a.m. to 5 p.m. each day. The improvement project is scheduled to be complete by the end of June 2016.

This pavement improvement project is part of the $100 million, five-year street bond program – Road Recovery. The Road Recovery program is funded by voter-approved bonds. More information on the Road Recovery Program can be found at https://www.tucsonaz.gov/street-bonds or by calling (520) 837-6686.