Speedway Boulevard - Second Avenue to Campbell Avenue Resurfacing Projects

On Wednesday, June 3, 2015, crews from Sunland Asphalt, under contract with the City of Tucson Department of Transportation (TDOT), will begin work to improve the pavement conditions on Speedway Boulevard from Second Avenue to Campbell Avenue. 

Crews will begin the project with the lowering of manhole covers and water valve covers. Lowering the utility covers is scheduled to be complete by Friday, June 5, 2015. Work will take place from 7 a.m. to 6 p.m. each day.

On Tuesday, June 9, 2015, crews will begin milling (removing asphalt) and repaving Speedway Boulevard. The paving work is scheduled to be complete by Thursday, June 11, 2015. To lessen the impact on the traveling public the milling and paving work will take place from 6 p.m. to 6 a.m. each night.

This pavement improvement project is part of the $100 million, five-year street bond program – Road Recovery. The Road Recovery program is funded by voter-approved bonds.

Residential and business access will be maintained at all times during the project, except for when heavy equipment is directly in front of a driveway.  At least one lane of travel in each direction will be maintained during this work. Please obey all traffic control signs and watch for construction personnel and equipment in these work areas. The schedule is subject to change due to equipment malfunction or inclement weather. 

More information on the Road Recovery Program can be found at https://www.tucsonaz.gov/street-bonds or by calling (520) 837-6686.