22nd street – Wilmot to Swan Road Resurfacing Project

On Wednesday, April 1, 2015, crews from Southern Arizona Paving and Construction Co., under contract with the City of Tucson Department of Transportation (TDOT), will begin work to improve the pavement conditions on 22nd Street from Wilmot Road to Swan Road.

Crews will begin the project by lowering manhole covers and water valve covers on 22nd Street from Wilmot Road to Craycroft Road. Work hours
will be 8 a.m. to 5 p.m. The utility work is scheduled to be complete by Friday, April 3, 2015.

On Monday, April 6, 2015, crews will begin milling (removing asphalt) and repaving 22nd Street. To lessen the impact on the traveling public,
the milling and paving work will take place at night from 6 p.m. to 6 a.m. The milling and paving work is scheduled to be complete by Friday,
May 8, 2015. During this work at least one lane of travel in each direction will be maintained.

This pavement improvement project is part of the $100 million, five-year street bond program – Road Recovery. The Road Recovery program is funded by voter-approved bonds.

Residential and business access will be maintained at all times during the project, except for when heavy equipment is directly in front of a
driveway. At least one lane of travel in each direction will be maintained during this work. Please obey all traffic control signs and watch for construction personnel and equipment in these work areas. The schedule is subject to change due to equipment malfunction or inclement weather.