ROAD RECOVERY SPEEDWAY BOULEVARD - ALVERNON WAY TO ROSEMONT BOULEVARD RESURFACING PROJECTS

On Monday, October 27, 2014, crews from Southern Arizona Paving and Construction Co., under contract with the City of Tucson Department of Transportation (TDOT), will begin work to improve pavement conditions on Speedway Boulevard from Alvernon Way to Rosemont Boulevard. Crews will begin the project by lowering manhole covers and water valve covers. Work hours will be 9 a.m. to 4 p.m. This work is scheduled to be complete by Friday, October 31, 2014.

Crews will return to this section of Speedway Boulevard on Sunday, November 2, 2014 to begin milling (removing asphalt) and paving operations. The milling and paving work is scheduled to be complete on Thursday, November 6, 2014. Work hours for the milling and paving work will be 6 p.m. to 6 a.m.

This pavement improvement project is part of the $100 million, five-year street bond program - Road Recovery. The Road Recovery program is funded by voter-approved bonds.

Residential and business access will be maintained at all times during the project, except for when heavy equipment is directly in front of a driveway. At least one lane of travel in each direction will be maintained during this work. Please obey all traffic control signs and watch for construction personnel and equipment in these work areas. The schedule is subject to change due to equipment malfunction or inclement weather.